Planning guarantee
The term ‘planning guarantee’ refers to the Government policy that no planning application should spend more than a year with decision-makers, including any appeal.
This means that planning applications themselves should be decided in no more than 26 weeks, allowing for a further 26 weeks to for any appeal. This should only be exceeded following a written agreement with the applicant, setting out the timescale within which a decision is expected.
This is in addition to the statutory time limits which set targets for planning authorities determine planning applications:
- Within 13 weeks for applications for major development.
- Within eight weeks for all other types of development (unless an application is subject to an Environmental Impact Assessment, in which case a 16 week limit applies).
If a valid application is not determined within the statutory period (or such other period as has been agreed) the applicant has a right to appeal to the Secretary of State against non-determination.
If the applicant does not exercised this right of appeal, and the application remains undetermined after 26 weeks, then the fee will be refunded.
Where planning authorities are designated as not adequately performing their function of determining applications, major development may be submitted directly to the Secretary of State. See Special measures designation for under-performing planning authorities for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.