Planning guarantee
The term ‘planning guarantee’ refers to the Government policy that no planning application should spend more than a year with decision-makers, including any appeal.
This means that planning applications themselves should be decided in no more than 26 weeks, allowing for a further 26 weeks to for any appeal. This should only be exceeded following a written agreement with the applicant, setting out the timescale within which a decision is expected.
This is in addition to the statutory time limits which set targets for planning authorities determine planning applications:
- Within 13 weeks for applications for major development.
- Within eight weeks for all other types of development (unless an application is subject to an Environmental Impact Assessment, in which case a 16 week limit applies).
If a valid application is not determined within the statutory period (or such other period as has been agreed) the applicant has a right to appeal to the Secretary of State against non-determination.
If the applicant does not exercised this right of appeal, and the application remains undetermined after 26 weeks, then the fee will be refunded.
Where planning authorities are designated as not adequately performing their function of determining applications, major development may be submitted directly to the Secretary of State. See Special measures designation for under-performing planning authorities for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.