Planning guarantee
The term ‘planning guarantee’ refers to the Government policy that no planning application should spend more than a year with decision-makers, including any appeal.
This means that planning applications themselves should be decided in no more than 26 weeks, allowing for a further 26 weeks to for any appeal. This should only be exceeded following a written agreement with the applicant, setting out the timescale within which a decision is expected.
This is in addition to the statutory time limits which set targets for planning authorities determine planning applications:
- Within 13 weeks for applications for major development.
- Within eight weeks for all other types of development (unless an application is subject to an Environmental Impact Assessment, in which case a 16 week limit applies).
If a valid application is not determined within the statutory period (or such other period as has been agreed) the applicant has a right to appeal to the Secretary of State against non-determination.
If the applicant does not exercised this right of appeal, and the application remains undetermined after 26 weeks, then the fee will be refunded.
Where planning authorities are designated as not adequately performing their function of determining applications, major development may be submitted directly to the Secretary of State. See Special measures designation for under-performing planning authorities for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Managing building safety risks
Across an existing residential portfolio, a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.